Slate’s been busy in Warsaw, Indiana. While the company’s product development team has been putting in long hours in Troy, Michigan and at test sites in the American West, Slate’s manufacturing facility is nearing completion and already producing vehicles.

The new manufacturing plant has two buildings, West and East, that will be used to bring customer vehicles to life.

“The team in Warsaw has been amazing on the progress that they've made,” Slate’s President of Vehicles Chris Barman told Newsweek. One year ago, the facility was still a shell with workers primarily taking out cement and digging floors. “All the floors are in, everything's there. We're well beyond that at this point,” she confirmed.

Read More on Autos

She continued: “The body shop is fully in and functional. We’re building all our body in whites to process now. It’s a slow process. You go through a slow build to make sure that you’re tuning in all the robots [and ensure that] all the welds are right.”

Body in white in an automotive industry term for the product that is the result of a joining of the main structural parts of a vehicle before it is painted.

“As we're building the bodies, some we send for our prototypes, and some, a fair number of those, we're actually taking and tearing down, because we want to make sure the quality is right. We want to make sure the welds are right, we want to make sure everything's there,” Barman said.

The units that are torn down receive an ultrasonic inspection. Before Slate team members physically disturb the unit, they use ultrasonic tools to see the integrity and size of the weld to ensure that they are the right size and dimension. It’s a vital step toward ensuring that Slate’s product will be high quality when it reaches customers.

Other parts of the production process are less finalized, including the electrodeposition coating (e-coating) area, where the bodies in white move after creation. There, they have rust prohibitor put on them, are moved through an oven, and bake. “I would say 70% of that is installed and in place. Around the end of summer is when we'll have that up and running,” she estimated.

The company has vertically integrated its bonding process and will be bringing that to Warsaw soon. Currently, Slate is working with their supplier in Howell, Michigan, running Slate’s parts at their facility. By the end of summer, they’ll take the bits of that process and move it south.

All of that will happen in the West building in Warsaw. The company just started digging at its East building two weeks ago, preparing to build the trestle that will take Slate truck bodies from the West to East. That trestle will also be up and running by the end of summer.

The General Assembly area of the plant is nearly ready with all four lines of trim in place. “We're doing a lot of the building of the structure where it's needed around [those lines], where, you hang tools or hang assist arms and things like that… They're still putting in some of the wiring. Everything's powered up, but we're just getting all of that put in in place,” Barman said.

Building of the two chassis lines started last week. Further, the company’s four-point shaker and buzz, squeak, rattle track have been installed. The seat line starts installation in mid-July. Wheel and tire operations will be in place by the end of the summer.

Barman isn’t just tracking the progress via video calls and emails. She’s on the ground, living part-time in Warsaw and spending half of her week, every week, on site, splitting her time between Indiana and Michigan.